NEW QUESTION # 106
What should a Scrum Master do when one team member falls behind in their tasks'?
- A. Move the task to another team member who has spare capacity in the sprint
- B. Privately offer the team member encouragement to meet task commitments
- C. Notify the product owner
- D. Ask the team for suggestions
Answer: D
NEW QUESTION # 107
A high-performance Agile team:
- A. is self-organizing, empowered to make decisions, and consensus-driven, with constructive disagreement.
- B. is fully committed to team success yet respects the prescribed roles and titles of team members.
- C. owns its decisions and commitments and is motivated to succeed at any cost.
- D. produces a high volume of business value through intensive collaboration and avoidance of conflict.
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION # 108
When are acceptance tests typically written for a user story?
- A. After writing the story, but before coding begins
- B. After estimating the Product Backlog, but before Sprint planning begins
- C. At the start of Product Backlog prioritization planning
- D. After coding the story, but before user acceptance testing begins
Answer: C
NEW QUESTION # 109
A technical problem arises that win likely impact the stories planned for delivery in the current sprint What should the scrum master do?
- A. Consider adding a story to the next sprint to seek resolution
- B. Ask the team to collaboratively work out a solution
- C. Engage a technical manager to assist With finding a solution
- D. immediately solve the problem on behalf of the team
Answer: B
NEW QUESTION # 110
What is the sequence of Tuckman's stages of team formation and development progress?
- A. Norming
- B. Performing
- C. Storming
- D. Forming
Answer: A,B,C,D
Explanation:
D, A, C, B (In that order)
NEW QUESTION # 111
A project sponsor is upset that an enhancement will be unavailable until next year.
What should the product owner do?
- A. Negotiate with the project sponsor for increased funding.
- B. Empower the project sponsor to manage the product backlog.
- C. Ensure that the project sponsor's priorities are in the product backlog.
- D. Accept responsibility for the product's delay.
Answer: C
NEW QUESTION # 112
Information transmission is greatest amongst team members who are working on:
- A. The same task through pair programming.
- B. The same group of tasks individually.
- C. Different tasks on the same project.
- D. Individual tasks in the same work area.
Answer: A
NEW QUESTION # 113
What are the primary outputs of a release planning session?
- A. Prioritized Product Backlog, risks, action items, and release goals
- B. Risks, action items, dependencies, and Release Backlog
- C. Release vision, assumptions, action items, and iteration goals
- D. Estimated iteration velocities, risks, action items, and Release Backlog
Answer: B
NEW QUESTION # 114
On a project using eXtreme Programming (XP), a customer test is a:
- A. Technique to determine if the software is easy for customer use.
- B. Technique to determine if a customer will use a software feature.
- C. Test for determining if a customer will purchase the product.
- D. Tool for a customer to verify the business requirements.
Answer: D
NEW QUESTION # 115 
Based on the backlog metrics in the chart, what can explain the Jump in points at the end of iteration 4?
- A. The team learned that the product owner needed to increase the output in the next release
- B. The team realized that some stories were underestimated relative to other stones and reestimated as needed
- C. The team neglected to account for support and maintenance costs associated with other supported products
- D. The team discovered that previously accepted work could be greatly improved and added story points associated with that work
Answer: B
NEW QUESTION # 116
Which of the following 2 statements are TRUE about Product Refinement? (Choose two.)
- A. Should take no more than 10% of the Development Team's time
- B. Multiple Scrum Teams may participate in this process
- C. The Product Owner is responsible for all estimates
- D. The Scrum Master facilitates these sessions
Answer: A,B
NEW QUESTION # 117
The purpose of the iteration retrospective is to:
- A. Prioritize the Product Backlog, generate development and testing estimates, and plan the next iteration.
- B. Identify what worked well, what did not work well, and what actions should be taken to improve the process.
- C. Provide a demonstration of the features developed during the iteration, get feedback from users, and begin testing.
- D. Report progress of the work effort, what work will be done next, and review impediments to progress.
Answer: B
NEW QUESTION # 118
Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can inferthat:
- A. Work was added to the Product Backlog.
- B. The team's velocity increased.
- C. Work was removed from the Product Backlog.
- D. The team's velocity decreased.
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION # 119
Well-written User Stories that follow the INVEST model include which attributes?
- A. Negotiate, Estimable, Small
- B. Independent, Negotiable, Smart
- C. Independent, Valuable, Timely
- D. Valuable, Easy-to-use, Timely
Answer: A
NEW QUESTION # 120
Which of the following is NOT one of the 5 common conflict types?
- A. Difference in prioritizing tasks
- B. Lack of communication
- C. Compensation anxiety
- D. Waiting on completion of task dependencies
- E. Working in silos
- F. Lack of role clarity
Answer: C
NEW QUESTION # 121
The definition of an Epic can be written using the acronym CURB. What does CURB stand for:
- A. Compound/Unknown/Risky/Basic
- B. Create/Update/Replace/Big
- C. Complicated/Unusual/Really/Big
- D. Complex/Unknown/Risky/Big
Answer: D
NEW QUESTION # 122
What is the first thing that a team should do to estimate user stories for a project?
- A. Sort the user stories according to priority.
- B. Define the story points measure.
- C. Schedule a team meeting to understand them.
- D. Estimate through function point analysis.
Answer: B
Explanation:
Explanation/Reference:
Explanation: